top of page
![](https://static.wixstatic.com/media/dd2697_203f6799611340bdbd07f3fb7f984329~mv2.jpg/v1/fill/w_980,h_654,al_c,q_85,usm_0.66_1.00_0.01,enc_auto/dd2697_203f6799611340bdbd07f3fb7f984329~mv2.jpg)
115 KV Line, Substation, And Switching Station
Location: Red Lake, Ontario
Description:
115 kV line construction with earth and rock mount pole structures
Substation and switching station construction
Micropiles, concrete foundations, slabs, and perimeter fencing.
ROW clearing and access road construction.
Value: $7.10 M
Completion Date: 2012
Owner: Goldcorp Inc.